Between Myrdal and Kårdal the railway line makes long curves with many tunnels to avoid areas exposed to avalanches and rockslides. The postcard shows the railway line past the Vatnahalsen station and down the mountainside towards Kårdal. To the extreme right we can see the construction road that was built from 1894-96. This road is today a part of the so-called Navvy Road.

Fotograf
Mittet
Eigar
Flåm utvikling

The Flåm Railway - built 1923-1940

On 10 July 1908, the Norwegian Parliament - Stortinget - decided to build a railway line between Myrdal and Flåm. The work was not begun until 1923, and only in 1946 was the railway line completely finished. Many people were involved in building the steepest railway line in Norway in a very difficult terrain. Over a distance of 20 kilometres there are 20 tunnels. In the period between 1924 and 1949 6.165.350 man-hours in all were carried out. For close to 20 years the valley of Flåmsdalen was the workplace for several hundred people.

Village people became railway workers

The railway construction in Flåm led to an emergence of a new industrial group. Quite a few people from the area were employed, either as transport workers or as railway workers. Some of the workers found their wives in the valley and settled down there. At many places both father and son worked at the construction sites. At first the workforce counted about 120 men. During the hard economic times after the First World War, fewer workers were employed, which meant that the work schedule could not be kept. The number of workers increased to 280 in 1937. In the war years an average of 75 persons worked at the sites. In addition to those who were permanently employed at the construction sites, many people were working with various transport jobs, and cooks and others who carried out various services were paid by the work teams.

Image
Her er fire mann på jobb i fjellsida over tunnelmunningen i Pinnali. Både fjellreinsking og stikking var farleg og vanskeleg. På dei brattaste stadene vart karane fira ned med tog. Dei slo inn jernklamrar i fjellet, slik at desse etter kvart vart ein slags stige nedover fjellsida. Dei som reinska slo inn hol etter hol og fylte borehola med dynamitt og sprengde laus slepper og farleg fjell.

Four men are working in the vertical mountainside above the tunnel mouth at Pinnali. Removing loose rocks and siting were both dangerous and difficult undertakings. In the steepest sections the men were lowered down by means of ropes. They fastened iron clamps to the rock and these could then be used as steps in a sort of ladder down the mountainside. Those who cleared rocks also drilled holes and filled them with dynamite to blast loose cracks and dangerous rocks.

Datering
1923-1930
Fotograf
Ukjend
Eigar
Flåm Utvikling

Workers' barracks

As there were few farms up along the valley, barracks had to be built to accommodate the workers. There were eight barracks in all; three at Myrdal, one at Kårdal, one at Berekvam and one at Høga in addition to two at Flatedalen between Høga and Flåm. The latter two were built as family barracks. In each barrack, 16 men shared four rooms. Some of those who had families lived in private quarters. The office workers lived in their own houses at Flåm and Myrdal. At Myrdal a complete local community grew up with a general store, sub-post office, long-distance telephone exchange and a school (from 1899 to 1982) which even had a swimming pool. At Berekvam there was also a school, sub-post office and general store, in addition to a small café at the post station. There the horses had to rest before starting on the final heavy leg up to Myrdal.

Life as a construction worker

It was heavy going indeed. Most people worked all day long, and most of the work was carried out by hand. They worked on contract and the piece rate was 1.60 to 1.70 kroner per hour. In addition, there was a special family allocation of five øre per person supported in the worker's household. This arrangement lasted until 1929. From 1930, a special mountain supplement was introduced - 10 øre per hour - on the upper section of the Flåm Railway from Myrdal down to the upper entrance to the Nåli tunnel. The work team had to pay for cook and blacksmith. The cook was paid 18-25 øre per day from each worker. The blacksmith sharpened the drills and repaired the tools that the work team had to provide themselves. The work team also paid for the dynamite they used. At first there were three labour unions at the construction sites. With improved communication, these three were united into one.

Image
Arbeidslag med hest og stubbebrytar, som vi ser til høgre bak arbeidslaget. Kvar stein vart løfta opp på muren med stubbebrytar, og fire mann drog steinen på plass med spett. Bergensbana, og seinare arbeidet med Flåmsbana, skapte ein arbeidarklasse i Aurland kommune. I 1900 kom 30 av 524, som hadde med anlegget å gjera, frå Aurland. Om sommaren auka talet då jernbana tok inn sesongarbeidarar. Mange av desse kom frå Flåm.

A work team with horse and a so-called stump puller, seen to the right behind the work team. Each rock was lifted up on the wall with a stump puller, and four men pulled the rock in place by means of levers. The Bergen Railway, and later on the Flåm Railway, created a working class in the municipality of Aurland. In 1900, 30 out of the 524 men who worked at the construction sites came from Aurland. In the summer months, this number increased as the railway then employed seasonal workers. Many of these came from Flåm.

Datering
1923-1940
Fotograf
Ukjend
Eigar
Dagrunn Skahjem. Aurland kommune. Lokalhistorisk arkiv
Image
Arbeidslag rundt 1932. Arbeidslaga vart plasserte med visse mellomrom langs heile banestrekninga etter som anleggsleiinga fann det mest tenleg. Difor stod det fleire ferdige banestrekningar, medan andre strekningar ikkje var påbyrja under dei åra bana vart bygd. Her ser vi frå venstre Ivar Kinden, Hans Ohnstad, Johannes Haugen, Arne Stenersen, Julius Johansen d.e.

A work team about 1932. The work teams were spread along the whole railway line as the construction managers decided. Consequently, some sections could be completed while others had not yet been started upon during the construction period. From left to right: Ivar Kinden, Hans Ohnstad, Johannes Haugen, Arne Stenersen, Julius Johansen, the elder.

Datering
Ca 1932
Fotograf
Ukjend
Eigar
Julius Johansen d.y. Aurland kommune, Lokalhistorisk arkiv

Tunnel construction

Because of the danger of avalanches and the difficult terrain, the Flåm Railway has 20 tunnels in all, with a total length of 5692.6 metres. This is close to one third of the whole distance. The longest tunnel measures 1341.5 metres. In addition, a number of "snow roofs" were built between Myrdal and Bakli. All tunnels, with the exception of Nåli and Vatnahalsen were drilled by hand. The tunnel work was far from safe. One man lost an arm and two men died in 1925 and 1938. Those who carried out the drilling were particularly exposed to drilling dust, and many workers probably died of silicosis or were afflicted with other diseases for the rest of their lives. In 1937, the workers were called in to Haukeland Hospital in Bergen for a medical check-up, and many of the workers were diagnosed with silicosis, but nothing was done.

Image
Alle tunnelane, med unnatak av Nåli og Vatnahalsen, vart drivne for hand. Det var stor slitasje på borestålet der det var harde bergartar. Ved Melhus var steinsorten så hard at dei ikkje kunne bora meir enn 2-3 cm før boren laut til smia. Under tunnelarbeidet var det ofte slik at to mann bora, to mann lasta og to stod for transporten. Inndrifta i tunnelane var som regel 2 m i veka.

All the tunnels, with the exception of Nåli and Vatnahalsen, were drilled by hand. The drills were quickly worn down where the bedrock was hard. At Melhus the bedrock was so hard that they could not drill more than two-three centimetres before the drills had to be sharpened. The work teams could consist of six men; two men drilled, two men loaded, and two men transported the excavated masses. The rate of progress was usually two metres a week.

Datering
1923-1940
Fotograf
Ukjend
Eigar
Aurland kommune, Lokalhistorisk arkiv

Snow avalanches and rockslides

There were several instances of avalanches and rockslides down the steep mountainsides in the valley of Flåmsdalen during the construction period. In the autumn of 1924, there was a major rockslide at Høga which blocked the railway line and the rural road. The slide was quickly cleared of rocks, but because of loose rocks, it was decided to build a tunnel past the slide-exposed area. However, this solution turned out to be too expensive. Instead the line was moved further out from the mountainside and a deep ditch was dug in towards the mountainside in order to "catch" any rocks that might fall from above. The road was moved to the other side of the valley with two new bridges.

In 1925, a snow avalanche hit Store Reppa, so the entrance to the planned tunnel was blocked. In April the same year, a big rockslide of 1000 cubic metres fell above Berekvam without destroying the railway line. In 1928, there were snow avalanches at Nåli, Blomheller tunnel and at Lille Reppa. Huge blocks of rock up to six cubic metres at Lille Reppa smashed the road bridge. The other avalanches did not have any serious consequences.

Image
Dette biletet frå Rjondefoss viser kor bratt og vanskeleg terreng dei måtte byggja jernbanelina i.

This postcard from the waterfall of Rjoandefossen is a good illustration of the steep and difficult terrain the workers had to cope with in constructing the railway line.

Datering
1923-1930
Fotograf
Ukjend
Eigar
Aurland kommune, Lokalhistorisk arkiv

The transport men

Many of those who carried out transport work for the railway also drove tourists. They transported tourists in daytime and at night they carried out transport of materials. This meant hard work for man and horse. They were actually not allowed to make more than three tours a day. For some time there was even a "horse police" who checked whether the horses were properly shod and were well taken care of. The transport to the construction sites could consist of food provisions, equipment, tools and other materials. Down from Myrdal they had to use packsaddles on the horses down the steep scree. The horses were also used to pull rocks and soil along the planned railway track.

Temporary opening

The Flåm Railway faced many difficulties. Many people wanted to stop the whole construction project, but neither natural disasters nor decreasing allocations could stop the progress, even if the work went slowly. In 1936, the work was started to lay the rail. The railway was temporarily opened on 1 August 1940 for goods traffic, after much pressure from the Germans. The reason was the need to transport materials to the aluminium plant that was being built at Årdal. On 10 February 1941, the railway line was opened for passenger traffic as well. From Myrdal down to Flåm the train took 65 minutes, whereas the uphill journey took 80 minutes. Today the driving time is 5o minutes either way.